Skip to content
MEGASTEELSStructural Steel Fabrication

Structural steel fabrication and erection timelines

Procurement · 5 min read

A steel package's programme is a chain of stages: drawing approval, steel procurement, detailing, fabrication, surface treatment, delivery and erection. There's no fixed duration; the real drivers are tonnage, complexity, how fast drawings are approved and mill lead times, and most of those you can influence.

The stages, in order

  1. Drawing approval: design drawings and connections signed off
  2. Detailing: shop drawings and the 3D model produced and approved
  3. Procurement: steel ordered, subject to mill and stockholder lead times
  4. Fabrication: cutting, drilling, welding and assembly
  5. Surface treatment: galvanising, paint or intumescent protection
  6. Delivery and erection: steel to site and the frame stood up in sequence

What actually drives the timeline

Two jobs of the same tonnage can have very different programmes. The biggest variables are:

  • How quickly the design team turns around drawing approvals
  • Steel procurement and mill lead times, which move with the market
  • Detailing complexity, which rises with connection design and the number of unique pieces
  • The surface treatment specified, as galvanising and intumescent add steps
  • Site readiness and the erection sequence

What compresses the programme

Complete, early information shortens everything downstream. So does ordering steel early against a firm design, and taking fabrication and erection as one package, which removes the hand-off between separate suppliers and keeps the whole job on one schedule.

What extends it

Late or changing approvals, design changes after detailing has started, special or long-lead materials, and constrained sites that limit deliveries or craneage all stretch the programme. Flagging these early lets us plan around them rather than re-plan mid-job.

Plan it against your project

The only honest timeline is one built against your drawings and programme. Send them over and we'll come back with a realistic fabrication and erection programme, not a generic number.

Common questions

How long does structural steel fabrication take?
There's no single answer. The programme depends on tonnage, complexity, how fast drawings are approved and steel mill lead times. The reliable way to get a timeline is to have it built against your actual drawings.
What's the biggest cause of steel programme delays?
Late or changing drawing approvals, and steel procurement lead times. Both sit early in the chain, so a slip there pushes everything downstream. Complete information and early sign-off are the best protection.
Can fabrication start before all drawings are approved?
Sometimes, through phased release: approved packages can proceed while others are finalised. It needs careful sequencing, but it can keep a programme moving when later areas are still being designed.

Send us your drawings for a quote

Get a Quote Call